Buried Coatings

Project Data

LocationPex Hill, UK
ClientNMCN
ContractorJMC North West Ltd
ProductsDenso P2 System - Denso Primer D, Denso Profiling Mastic and Densoclad Tape
DateAugust 2020

Project Details

As part of United Utilities water quality improvement programme, JMC North West Ltd, on behalf of NMCN, recently completed works to bury the above ground timing loop at the Pex Hill Service Reservoir. The challenge was to provide a durable, reliable corrosion prevention solution to protect over 90 double flanged joints prior to full encapsulation. To provide this high level of protection, JMC North West Ltd turned to Winn & Coales (Denso) Ltd for their services.

Winn & Coales recommended their Denso P2 System, proven to effectively protect ferrous pipes, joints and fittings from the costly effects of corrosion. Fully compliant with the P2 Civil Engineering Specifications for the Water Industry (7th Edition), this time-proven system can be easily applied on-site before the pipe is buried – providing long-term corrosion prevention for the project at Pex Hill. The Denso P2 System incorporates Denso Primer D, Denso Profiling Mastic and Densoclad Tape. Training on how to apply the system was provided, on-site, by two members of the Winn & Coales (Denso) Ltd team.